City of Hope
A high-pressure steam line was discovered to have a leak. The line was
crucial for the operations of the hospital. Darryl Wilson, of the Hospital explains what
happened:
An underground high-pressure steam line leak was discovered the day after Christmas in
an area of difficult access and high traffic. The leaking line ended up being one of the
main feed lines to the hospital and the food service operations on the campus. Moe
Plumbing provided immediate service and coordinated among a host of required trades.
Moe stayed on the job up to 16 hours a day and seven days a week to deliver a permanent
duty system which was installed without any interruption to the hospital or services.